FBLA Project Management practice test

Project Management covers planning, executing, and closing projects: scope, schedules, budgets, risk, and stakeholders, using vocabulary from the Project Management Institute (PMI).

Topics on the FBLA Project Management test

  • Project life cycle and process groups
  • Scope and the work breakdown structure (WBS)
  • Scheduling, critical path, and Gantt charts
  • Budgeting and cost control
  • Risk and quality management
  • Stakeholders, communication, and agile methods

Free FBLA Project Management practice questions and answers

Try each question before opening the answer. Every AI practice test explains its answers the same way.

  1. Question 1

    The longest sequence of dependent tasks, which sets the shortest possible project duration, is the:

    1. ACritical path
    2. BWork breakdown structure
    3. CScope statement
    4. DMilestone
    Show answer

    Answer: A. Critical path

    Any delay to a task on the critical path delays the whole project, because those tasks have no slack.

  2. Question 2

    A document that breaks project deliverables into smaller, manageable pieces of work is a:

    1. AGantt chart
    2. BWork breakdown structure (WBS)
    3. CRisk register
    4. DProject charter
    Show answer

    Answer: B. Work breakdown structure (WBS)

    The WBS decomposes the scope into work packages. A Gantt chart then schedules that work over time.

  3. Question 3

    In Scrum, a short, fixed-length period in which the team completes a set amount of work is a:

    1. ASprint
    2. BPhase gate
    3. CMilestone
    4. DBaseline
    Show answer

    Answer: A. Sprint

    Sprints usually last one to four weeks and end with a review and a retrospective.

How to study for FBLA Project Management

Practice finding the critical path on a small network diagram by hand, and know the difference between a project charter, a scope statement, and a WBS.

Read the full FBLA study guide

Want more Project Management questions?

Generate a 5, 10, or 25 question Project Management practice test with new questions every time, explanations for every answer, and your scores saved to your dashboard. It’s free.

Start practicing free

FBLA Project Management FAQ

How many questions are on the FBLA Project Management test?

Project Management is an objective test event. Under the current guidelines, FBLA objective tests are typically 100 multiple-choice questions in 50 minutes. Check the official FBLA competitive event guidelines for your season and conference.

What topics are on the FBLA Project Management test?

Expect questions on project life cycle and process groups; scope and the work breakdown structure (WBS); scheduling, critical path, and Gantt charts; budgeting and cost control; risk and quality management; and stakeholders, communication, and agile methods.

Are these official FBLA Project Management questions?

No. The sample questions are original and written in the style of FBLA objective tests. TierOne is an independent study aid and is not affiliated with FBLA.